For communities living with data centers
A resource for communities considering whether to host data centers, dealing with existing ones, or resisting them: what works, what doesn't, and the public record.
What you'll find here
We collect public information so that residents and local officials can see what other places have negotiated, and what has gone wrong elsewhere, before they decide.
Practices
Agreements and commitments that communities and researchers have pointed to, with what critics say is still missing.
Documented issues
Cases where a regulator or government put a problem on record, with the operator's response.
Sources, always
Every entry links to where it came from. We do not endorse or oppose any company or project.
Practices communities have pointed to
Three of the five entries on record. See all practices.
-
Practice
Lancaster, Pennsylvania
A 20-year community benefits agreement
Lancaster signed a 20-year community benefits agreement covering three data centers on two campuses. It caps municipal water use at 20,000 gallons a day per campus, requires closed-loop cooling and clean-energy sourcing backed by a $10 million letter of credit, and commits $20.25 million to a community foundation and a city clean energy fund.
What reviewers say is missing: Reviewers at Columbia's Sabin Center also note gaps: no decibel limit for noise, no stated megawatt demand, and no minimum for local hiring. A community group said it saw the text two days before the council vote.
-
Practice
Cedar Rapids, Iowa
A tax break tied to jobs and payments
Cedar Rapids negotiated a "community betterment" agreement with Google and QTS. A 20-year, 70 percent tax exemption is conditioned on meeting a job threshold and a minimum wage. Google agreed to pay $400,000 over 15 years and QTS $18 million over 18 years.
Source: Brookings, January 29, 2026
-
Practice
El Paso, Texas
Water and reporting commitments in exchange for an abatement
Meta's $1.5 billion El Paso data center received an 80 percent property tax abatement over 35 years. In return the company specified average water use starting at 750,000 gallons a day, committed to closed-loop cooling, and promised annual public reports on water and electricity use.
Source: Brookings, January 29, 2026
Documented issues
Three of the five entries on record. See all documented issues.
-
Documented issue
Leesburg, Virginia
Microsoft and Virginia DEQ
Virginia DEQ announced a consent order with a civil penalty of roughly $2.5 million against Microsoft over its Leesburg data center, which the agency described as its largest for a data center. DEQ found backup generators exceeded air pollution limits during a substation outage from June 27 to July 1, 2025, and that the site used about 1.19 million gallons of fuel in a year against a 665,850-gallon limit. Microsoft signed the order, which was open for public comment through October 14, 2026.
Response on record: Microsoft said it worked with the state toward a resolution, will support expanded air monitoring in Northern Virginia, and invested about $31 million to prevent another extended outage.
Source: WJLA, September 15, 2026
-
Documented issue
Vineland, New Jersey
Data One and NJ DEP
New Jersey DEP fined Data One $1.07 million after a July 2026 inspection found 62 large natural-gas generators operating without required air permits. The state called it the largest enforcement action against a data center in New Jersey.
Response on record: Data One said it disagrees with the state's determination, will apply for permits for the temporary generators, and is moving to low-emission fuel cells as permanent power.
Source: 6abc, September 23, 2026
-
Documented issue
Newton County, Georgia
Serverfarm, VoltaGrid and Georgia EPD
Georgia EPD fined Serverfarm $31,000 and VoltaGrid $11,500 through consent orders for installing generators and engines before construction permits were issued. The orders state they are not a finding or admission of a violation of state law.
Response on record: Both companies cited a misunderstanding about what work was allowed. Serverfarm said no generator was fueled or run before its permit.
Source: WTOC, October 7, 2026
Terms other communities have put in writing
Each item below appears in at least one agreement or commitment in the record. Whether it suits your community is for you to judge.
- A cap on water use, stated in gallons per day (Lancaster, El Paso).
- Closed-loop cooling (Lancaster, El Paso).
- Clean-energy sourcing backed by money, such as a letter of credit that pays out on noncompliance (Lancaster).
- Payments to community funds on a fixed schedule (Lancaster, Cedar Rapids).
- Tax breaks conditioned on jobs and wages (Cedar Rapids).
- Annual public reporting on water and electricity (El Paso).
- Negotiations without NDAs (Microsoft).
- Noise limits in decibels: reviewers flagged their absence in Lancaster, and Loudoun County is rewriting its rules.